All checks were successful
CI / Get Changed Files (pull_request) Successful in 30s
Pull Request Labeler / labeler (pull_request_target) Successful in 15s
CI / Backend Tests (pull_request) Has been skipped
Label PRs based on size / Check PR size (pull_request) Successful in 29s
CI / eslint (pull_request) Has been skipped
CI / Checkstyle Main (pull_request) Has been skipped
CI / oxlint (pull_request) Has been skipped
CI / Docker frontend validation (pull_request) Has been skipped
CI / prettier (pull_request) Has been skipped
CI / Docker backend validation (pull_request) Has been skipped
CI / test-build (pull_request) Has been skipped
CI / Playwright (pull_request) Has been skipped
Claude PR Review / claude-code (pull_request) Successful in 1m42s
13 lines
620 B
TeX
13 lines
620 B
TeX
% Table generated by Excel2LaTeX from sheet 'Zeitnachher'
|
|
\begin{tabular}{lrrr}
|
|
\rowcolor{heading}\textbf{Phase} & \textbf{Geplant} & \textbf{Tatsächlich} & \textbf{Differenz} \\
|
|
\textbf{Analysephase} & 6 h & 6 h & \\
|
|
\rowcolor{odd}\textbf{Entwurfsphase} & 14 h & 14 h & \\
|
|
\textbf{Implementierungsphase} & 37 h & 28 h & -9 h \\
|
|
\rowcolor{odd}\textbf{Abnahmetest der Fachabteilung} & 5 h & 5 h & \\
|
|
\textbf{Einführungsphase} & 1 h & 1 h & \\
|
|
\rowcolor{odd}\textbf{Erstellen der Dokumentation} & 8 h & 17 h & +9 h \\
|
|
\hline
|
|
\hline
|
|
\rowcolor{odd}\textbf{Gesamt} & 70 h & 70 h & \\
|
|
\end{tabular}
|