All checks were successful
CI / Get Changed Files (pull_request) Successful in 30s
Pull Request Labeler / labeler (pull_request_target) Successful in 15s
CI / Backend Tests (pull_request) Has been skipped
Label PRs based on size / Check PR size (pull_request) Successful in 29s
CI / eslint (pull_request) Has been skipped
CI / Checkstyle Main (pull_request) Has been skipped
CI / oxlint (pull_request) Has been skipped
CI / Docker frontend validation (pull_request) Has been skipped
CI / prettier (pull_request) Has been skipped
CI / Docker backend validation (pull_request) Has been skipped
CI / test-build (pull_request) Has been skipped
CI / Playwright (pull_request) Has been skipped
Claude PR Review / claude-code (pull_request) Successful in 1m42s
12 lines
409 B
TeX
12 lines
409 B
TeX
% Table generated by Excel2LaTeX from sheet 'ZeitplanungKurz'
|
|
\begin{tabular}{lr}
|
|
\rowcolor{heading}\textbf{Projektphase} & \textbf{Geplante Zeit} \\
|
|
Analysephase & 6 h \\
|
|
\rowcolor{odd}Entwurfsphase & 14 h \\
|
|
Implementierungsphase & 37 h \\
|
|
\rowcolor{odd}Abnahmetest der Fachabteilung & 5 h \\
|
|
Erstellen der Dokumentation & 8 h \\
|
|
\hline
|
|
\hline
|
|
\rowcolor{odd}\textbf{Gesamt} & \textbf{70 h} \\
|
|
\end{tabular}
|